Speechly Bircham | Inform: Construction & engineering - Yuanda (UK) Co Limited v WW Gear Construction Limited case insight

June 2010


Inform: Construction & engineering

Yuanda (UK) Co Limited v WW Gear Construction Limited case insight 

 

Speechly Bircham

 

A recent decision in the TCC has addressed a number of important issues, including: "Tolent" clauses; what happens when contractual adjudication provisions are found to be non-Act compliant; whether joinder provisions in adjudication clauses are permissible and the minimum rate of interest for late payments.

 

If you wish to discuss any aspect of the insight below or require further information about the services provided by our construction and engineering team, please don't hesitate to contact us.

 

 

 Yuanda (UK) Co Limited v WW Gear Construction Limited

 

  

The dispute arose out of the construction of a new hotel in the old GLC building by Westminster Bridge. Gear was the client and Yuanda was the trade contractor responsible for the glazed curtain walling.


"Tolent" clauses


The relevant clause provided that "...regardless of the eventual decision in the adjudication ... the Trade Contractor agrees that should he make a reference to Adjudication ... he will be fully responsible for ... the Employer's legal and professional costs in relation to the Adjudication".


A similar (but not identical) provision had been considered permissible since the case of Bridge Construction v Tolent Construction in 2000. However, these clauses are regarded by many as particularly unfair on sub-contractors and are to be out-lawed when the new Local Democracy, Economic Development and Construction Act 2009 comes into force.
 

In this case, the Court decided to pre-empt the new Construction Act by reversing the decision in Tolent, although it made it clear that the spectre of the new Act had not influenced the decision.
 

The Court decided that this particular "Tolent" clause was non-compliant with the Housing Grants, Construction and Regeneration Act (HGCRA) 1996 because it effectively deprived the referring party of its remedy up to the costs of the responding party, over which it had no control. The clause also acted as a real restriction on a party's ability to commence an adjudication "at any time" because it discouraged disputes being referred until the sum in dispute was sufficiently large, bearing in mind the likely costs of the responding party.
 

So what adjudication provisions applied?


Based upon the wording contained in section 108(5) of the HGCRA 1996, it was held that if one part of the adjudication provision was non-compliant then all the adjudication provisions in the contract were replaced in their entirety by the Scheme. The Scheme did not merely plug the gaps in any non-compliant aspects of the contractual adjudication provisions.
 

This can be contrasted with the position with payment provisions.  In that situation, the Court indicated that clauses from the Scheme would only replace specifically non-compliant clauses in the contractual provisions. The remainder of the payment provisions agreed by the parties would remain in force – unless the only feasible solution was to replace the contractual provisions in their entirety with the Scheme.


Do joinder provisions in adjudication clauses comply with the HGCRA 1996?
 

The Court held such provisions could be compliant with the HGCRA 1996.
 

For example, the question whether a defect was down to bad workmanship or negligent design was one dispute that may involve a number of parties. It would therefore not fall foul of the rule that only one dispute can be adjudicated at one time (without the consent of the other party). However, it would be a separate dispute to determine the liability of the contractor as opposed to the liability of, say, the architect. Therefore, joinder provisions could only be valid insofar as they were limited to making the adjudicator's decision binding on the joined party and did not extend the scope of the original adjudication.
 

Late Payment of Commercial Debts (Interest) Act 1998
 

The statutory rate of interest for late payment of commercial debts is 8% over base.
 

However, if the contract specifies "a substantial contractual remedy for late payment of the debt", then the contractual rate will take precedence.
 

The Joint Contracts Tribunal (JCT) standard forms contain an interest rate of 5% over base for late payment. However, in this case, this had been amended to only 0.5% over base.
 

The Court held that this was not a "substantial remedy" and therefore the applicable rate of interest would be 8% over base.  However, it is interesting to note that the Court indicated that it could see no reason why the rate of 5% above base in an unamended JCT would not be a "substantial remedy"; and would therefore oust the statutory rate. The Court also considered it likely that a rate of 3-4% above base would be a "substantial remedy".
 

Conclusion
 

This decision puts into serious doubt the efficacy of any Tolent clause. The particular clause in question only enabled one side (the Employer) to recover all its costs. The clause in Tolent obliged whoever was the referring party to pay. Whilst it could be argued that such reciprocity makes the clause fairer, it is generally accepted that the responding party is likely to be the paymaster so the effect is to all intents and purposes, the same. Such a clause is still a real restriction on a party's ability to commence an adjudication "at any time".

 

Even watered down Tolent clauses that only require the referring party to pay the adjudicator's costs (and not the other party's legal costs) notwithstanding the outcome of the adjudication, are likely to be held to be non-compliant with the HGCRA 1996 following this decision because they still act as a restriction on a party's ability to adjudicate "at any time".
 

Once a non-compliant adjudication provision has been identified, the whole adjudication procedure goes (no matter how easy it is to have severed provisions) and is replaced in its entirety by the Scheme. Thus, other provisions that may have been beneficial to the smooth running of the process or are to the benefit of one of the parties (such as a preferred nomination body) are lost and the parties could end up with a dispute resolution clause different to the one they had originally agreed.
 

 

James Worthington, Solicitor, Speechly Bircham

+44 (0)20 7427 1070

james.worthington@speechlys.com

 


Seminar programme

Contractual Challenges: from conception to close out

 

This is an essential refresher course designed to help you:

  • effectively manage risk and protect interests when managing projects;
  • ensure you have the right foundations in place; and
  • advise you on the necessary steps to avoid costly disputes.

Click here for more details and to register

 

Recent insight

Pilon v Breyer case insight
A rare occurrence of the Court finding an adjudicator's decision unenforceable in its entirety.

 

Beck Interiors Limited v Dr Russo case insight
How an improperly drafted guarantee allowed a guarantor to escape liability.

 

Project Bank Accounts
How beneficial are they to the construction industry?

 

 

www.speechlys.com/
construction_
and_engineering
 

Request further information

Request further information

 

people.JPG

 

Forward this email to your colleagues

Lawyers you can talk to...

We have over 70 lawyers working in multidisciplinary teams to provide advice in:

 

Construction & engineering

 

Development

 

Projects

 

Real estate disputes

 

Real estate finance

 

Real estate investment

 

Real estate tax

 

Regeneration

 

Sustainability

 

UK & international occupiers

 

 



Speechly Bircham LLP is a limited liability partnership registered in England and Wales (registered number OC321620) and is regulated by the Solicitors Regulation Authority. A list of members' names is open to inspection at our registered office, 6 New Street Square, London EC4A 3LX

This information is correct to the best of our knowledge and belief at the time of going to press. It is, however, written as a general guide, so we recommend that specific professional advice is sought before any action is taken.

Speechly Bircham LLP 6 New Street Square, London EC4A 3LX
Tel +44 (0)20 7427 6400 Fax +44 (0)20 7427 6600
To opt out from future communications, please visit:
http://info.speechlys.com/vtu/kj608671qxc58lp


Concep | Our interactive email partner